Road Paving Projects Continue This Week

Upcoming Road Paving Work

The following roads are part of the Township's 2019 road paving schedule; some projects will continue into 2020, as well, depending upon weather conditions. Below is a summary of what roads are being paved when over the next few months

Rutgers/Hamilton/Princeton - Preconstruction meeting held week of 10/28/19. Topline Construction will begin doing concrete for curbing, ramps, depressed curbs for driveways, etc… week of November 18. (Rutgers from Hamilton to Mountain, Hamilton from Park to Princeton, Princeton from Park to just past Hamilton)

Briarwood East/West, Fay Place, Ridgewood Place – Preconstruction meeting was held week of 10/28/19. Topline Construction will begin doing concrete for curbing, ramps, depressed curbs for driveways, etc… week of November 18.

Saw Mill & Cornell - Work will be completed by Monday, November 25. 

Lawrence Drive – Complete; underdrains were inserted to improve drainage, and road was repaired. 

Cedar Green, Pine Grove, Scott & Surrounding Roads - Markouts complete; drainage improvements and corresponding road repair to begin after Thanksgiving. 

The 2019 capital budget was passed in August; it was at this point money was available for road paving projects. 